− | ==Process== | + | ==OCP Ready Facility Recognition Process== |
+ | # Complete self-audit of OCP Colo Facility Guidelines and Site Assessment | ||
# Contact Data Center Facility Project Lead | # Contact Data Center Facility Project Lead | ||
− | # | + | # Review Site Assessment and supporting information with Project Lead |
− | |||
− | |||
# Present to Data Center Facility Project Community | # Present to Data Center Facility Project Community | ||
# Receive approval from Incubation Committee | # Receive approval from Incubation Committee | ||
− | # Complete requirements for | + | # Execute OCP Ready Certification Mark Agreement |
+ | # Complete requirements for Colo Solution Provider | ||
==Requirements== | ==Requirements== |
Revision as of 12:26, 23 January 2019
Contents
Welcome
- Welcome to the OCP Data Center Facility Project: OCP Ready Program Information Page
Contacts
- - Brevan Reyher - OCP Data Center Facility Project Lead - brevan.reyher@ocproject.net
- - Mark Dansie - OCP Ready EMEA Lead - mark.dansie@inflectiontech.net
- - TBD - OCP Ready Americas Lead -
- - TBD - OCP Ready APAC Lead -
OCP Ready Facility Recognition Process
- Complete self-audit of OCP Colo Facility Guidelines and Site Assessment
- Contact Data Center Facility Project Lead
- Review Site Assessment and supporting information with Project Lead
- Present to Data Center Facility Project Community
- Receive approval from Incubation Committee
- Execute OCP Ready Certification Mark Agreement
- Complete requirements for Colo Solution Provider
Requirements
- Must be a OCP Tiered Corporate Member in good standing
- Must be a OCP Ready recognized facility
- Must be a Colo Solution Provider (CSP)
OCP Ready Facility Recognition Program
- Completed self-audit and recognition process
- Executed legal agreeements (OCP Ready Certification Mark Agreement)
Colo Solution Provider
- Executed legal agreements (Membership, CSP, Copyright)
- Paid applicable Membership and CSP fees
- Published landing page on website for inbound OCP leads
Benefits
- OCP Corporate Logo associated with Membership level
- OCP Ready™ certification mark for website
- OCP Solution Provider logo
- Listing on OCP Marketplace
- Google analytic reports provided quarterly from OCP team
- Contribution Points toward Membership requirements
Documentation
Colo Facility Guidelines for OCP Racks V1.1